Financial Audit of the Gomal Zam Dam Command Area Development Project in Pakistan Managed by the Government of Khyber Pakhtunkhwa Agriculture, Livestock and Cooperatives Department, Grant 391-DOA-GZDCADP-001-001, July 1, 2019, to June 30, 2020

Recommendations

Recommendation
1

Determine the allowability of $28,197 in questioned cost-sharing contributions (ineligible) as detailed in Findings 4.4.2, 4.2.3, and 4.2.4 on pages 34-37 of the report, and recover any amount that is unallowable.

Questioned Cost
28197
Funds for Better Use
0
Close Date
Recommendation
2

Determine the allowability of $168,316 (ineligible) in questioned amounts related to penalty not imposed to contractors on delayed completion of work as detailed in Finding 4.1.2 on pages 31-32 of the report, and recover any amount that is unallowable.

Questioned Cost
168316
Funds for Better Use
0
Close Date
Recommendation
3

Determine the allowability of $1,250,424 (ineligible) in questioned costs as detailed in Table 1 on page 2 of this memorandum, and recover any amount that is unallowable.

Questioned Cost
1250424
Funds for Better Use
0
Close Date
Recommendation
4

Determine the allowability of $2,640,051 (ineligible) in questioned amounts related to cumulative payments as of June 2020 to various contractors on construction works that were not in accordance with rules and procedures as detailed in Finding 4.4.1 on pages 40-41 of the report, and recover any amount that is unallowable.

Questioned Cost
2640051
Funds for Better Use
0
Close Date