Audit of USAID/Pakistan's Design for Sustainability in the Jamshoro Thermal Power Station Repair and Rehabilitation Project

Recommendations

Recommendation 1

USAID/Pakistan implement a plan to engage with the Government of Pakistan continually to promote policy reform in the energy sector.

Questioned Cost:
$0
Close Date:
Recommendation 2

USAID/Pakistan review and revise in writing the Jamshoro Thermal Power Station Project's target date for increasing energy capacity by 150 megawatts.

Questioned Cost:
$0
Close Date:
Recommendation 3

USAID/Pakistan update the capacity-building schedule for the Jamshoro Thermal Power Station to reflect an achievable completion date and document the results.

Questioned Cost:
$0
Close Date: