Financial Audit of IKP Knowledge Park Under Multiple USAID Agreements in India, April 1, 2017, to March 31, 2018

Recommendations

Recommendation 1

USAID/India verify that IKP Knowledge Park corrects the five instances of material noncompliance identified in the report on compliance on pages 37-40 and detailed in Annexure I (Questioned Costs) and Annexure to noncompliance (Findings 1-3) on pages 41-45 of the audit report.

Questioned Cost:
$0
Funds For Better Use:
$0