Audit of USAID/Pakistan's Design for Sustainability in the Jamshoro Thermal Power Station Repair and Rehabilitation Project

Recommendation
1

USAID/Pakistan implement a plan to engage with the Government of Pakistan continually to promote policy reform in the energy sector.

Questioned Cost
0
Close Date
Recommendation
2

USAID/Pakistan review and revise in writing the Jamshoro Thermal Power Station Project's target date for increasing energy capacity by 150 megawatts.

Questioned Cost
0
Close Date
Recommendation
3

USAID/Pakistan update the capacity-building schedule for the Jamshoro Thermal Power Station to reflect an achievable completion date and document the results.

Questioned Cost
0
Close Date