Financial Audit of the Khyber Pakhtunkhwa Reconstruction Program in Pakistan Managed by the Provincial Reconstruction Rehabilitation and Settlement Authority, Provincial Disaster Management Authority, Agreement 391-011, for the year ended June 30, 2022

Recommendations

Recommendation
1

Determine the allowability of $1.354 million in ineligible questioned costs detailed on pages 27 to 38 of the audit report and recover any amount that is unallowable.

Questioned Cost
1354000
Funds for Better Use
0