Audit of USAID/Yemen's Community Livelihoods Project

Recommendations

Recommendation
1

USAID/Yemen finalize its approach for the remainder of the Community Livelihoods Project by formally modifying the cooperative agreement.

Questioned Cost
0
Close Date
Recommendation
2

USAID/Yemen require Creative Associates International Inc. to update its project and performance management plans to reflect the changes in the modification.

Questioned Cost
0
Close Date
Recommendation
3

USAID/Yemen perform a documented review of its standard operating procedures with the Yemen Monitoring and Evaluation Project and, if necessary, amend the procedures to improve the communication of key findings.

Questioned Cost
0
Close Date
Recommendation
4

USAID/Yemen require Creative Associates
International Inc. to implement a performance management plan that includes the Yemen Monitoring and Evaluation Project's role, authorities, and responsibilities as thirdparty
monitors for the Community Livelihoods Project, as outlined in the mission's procedures.

Questioned Cost
0
Close Date
Recommendation
5

USAID/Yemen require Creative Associates
International Inc. to update its performance management plan to include a control system to validate the delivery of goods.

Questioned Cost
0
Close Date
Recommendation
6

USAID/Yemen require Creative Associates
International Inc. to update its performance management plan to clearly delineate its
responsibility for monitoring project activities and reporting findings in an accurate, timely
fashion.

Questioned Cost
0
Close Date
Recommendation
7

USAID/Yemen require Creative Associates
International Inc. to improve its data reporting by consolidating the data system, implementing a procedure manual to formalize data collection, and implementing a data validation system.

Questioned Cost
0
Close Date
Recommendation
8

USAID/Yemen deobligate funds associated with activities eliminated from the project.

Questioned Cost
0
Close Date
Recommendation
9

USAID/Yemen conduct a written analysis to
determine whether the project would benefit from creating a new funds control system. If so, it should implement the system to track funds for the remainder of the project.

Questioned Cost
0
Close Date