Audit of USAID/Pakistan's Design for Sustainability in the Jamshoro Thermal Power Station Repair and Rehabilitation Project
Recommendations
Recommendation
              1
          USAID/Pakistan implement a plan to engage with the Government of Pakistan continually to promote policy reform in the energy sector.
Questioned Cost
              0
          Close Date
              Recommendation
              2
          USAID/Pakistan review and revise in writing the Jamshoro Thermal Power Station Project's target date for increasing energy capacity by 150 megawatts.
Questioned Cost
              0
          Close Date
              Recommendation
              3
          USAID/Pakistan update the capacity-building schedule for the Jamshoro Thermal Power Station to reflect an achievable completion date and document the results.
Questioned Cost
              0
          Close Date