Review of USAID/Pakistan's Cost Estimates for Shipping and Storage
Recommendations
Recommendation
1
USAID/Pakistan establish and implement a procedure to more accurately estimate obligations for shipping and storage of goods and reduce the standard obligation from $25,000 to $15,000, resulting in an estimated $480,000 annually and $2.4 million over 5 years that could be put to better use.
Questioned Cost
0
Close Date
Recommendation
2
USAID/Pakistan review unliquidated obligations of an estimated $860,000 for fiscal years 2008-2010 and deobligate funds no longer needed.
Questioned Cost
0
Close Date