Audit of USAID/Bangladesh's Integrated Protected Area Co-Management Project

Recommendations

Recommendation
1

USAID/Bangladesh direct the International Resources Group to prepare a sustainability plan for the co-management organizations that will identify potential barriers to sustainability, and describe the project's plans to overcome such barriers.

Questioned Cost
0
Close Date
Recommendation
2

USAID/Bangladesh, in conjunction with the Government of Bangladesh, develop and implement an action plan to obtain required government-matched funds for the project's habitat restoration and infrastructure activities.

Questioned Cost
0
Close Date
Recommendation
3

USAID/Bangladesh require the International Resources Group to comply with the branding and marking policy and submit a written request to the mission for a waiver to use the Nishorgo Network name and logo on appropriate project documents and signage.

Questioned Cost
0
Close Date