Recommendation Dashboard

OIG makes recommendations in our reports to improve the efficiency and effectiveness of agency programs and help agencies identify questioned costs and funds that could be put to better use. The aim is to spur our audited agencies to take corrective actions, which allow us to close the recommendations.

This dashboard identifies current open recommendations along with the associated questioned costs.  Open recommendations may be resolved or unresolved:

  • A recommendation is resolved when OIG agrees with the agency's plan of action.
  • A recommendation is unresolved when the agency has yet to share a plan of action or OIG disagrees with the plan.

The dashboard below may not reflect accurate numbers due to temporarily unavailable resources. We apologize for any inconvenience. Please check back soon.

 

Total Open Recommendations (As of 12/12/24)

266

Open Financial Recommendations (As of 12/12/24)

$50,359,279


Please see an updated list of recommendations with their corresponding report below.

2010

Nov 10, 2009
Audit Report
5-306-10-002-P
Recommendation
1

USAID/Afghanistan require that its training on statement-of-work preparation be provided to all new contracting officer's technical representatives.

Questioned Cost
0
Close Date
Dec 01, 2010
Recommendation
2

USAID/Afghanistan develop procedures, such as the use of quality control checklists, to ensure that statements of work include such critical elements as clear deliverables with specified due dates.

Questioned Cost
0
Close Date
Nov 10, 2009
Recommendation
3

USAID/Afghanistan establish procedures requiring that a labor skills assessment be performed by a contractor, either upon award of a construction contract or upon the award of a task order under the contract. The assessment would include, as appropriate but not limited to, the availability of qualified local labor, vocational training needed to cultivate local labor, and plans to coordinate with the mission to obtain appropriate visas for non-Afghan labor.

Questioned Cost
0
Close Date
Nov 10, 2009
Recommendation
4

USAID/Afghanistan establish written procedures to ensure that all significant construction projects have onsite quality assurance engineers.

Questioned Cost
0
Close Date
Sep 29, 2010
Recommendation
5

The mission develop an overall implementation plan for the Kabul power plant project that incorporates updated construction schedules for the contractor and subcontractor, identifies delays in critical tasks, and establishes steps to keep the project on track.

Questioned Cost
0
Close Date
Nov 10, 2009
Recommendation
6

USAID/Afghanistan develop a comprehensive sustainability plan that includes considerations for anticipated fuel purchases as well as the impact and timing of future mission projects affecting the 105-megawatt plant.

Questioned Cost
0
Close Date
Nov 10, 2009
Recommendation
7

USAID/Afghanistan prepare a detailed implementation plan that documents the current status of the Kajakai project and explains how the mission intends to proceed with installation of turbine 2, including potential barriers to successful installation of the turbine and contingency plans to overcome these barriers.

Questioned Cost
0
Close Date
Feb 28, 2011
Recommendation
8

USAID/Afghanistan recover at least $2.1 million (including interest imputed through May 13, 2009) from the contractor.

Questioned Cost
2078426
Close Date
Nov 10, 2009
Oct 30, 2009
Audit Report
1-520-10-001-P
Recommendation
1

USAID/Guatemala's follow-on democracy and governance program aim to implement reforms at sufficient scale to achieve transformational impact.

Questioned Cost
0
Close Date
Oct 30, 2009
Recommendation
2

USAID/Guatemala include support for civil society advocacy efforts in its follow-on program or arrange for such support in coordination with other donors.

Questioned Cost
0
Close Date
Oct 30, 2009
Recommendation
3

USAID/Guatemala condition further efforts to train Government of Guatemala employees on progress toward civil service reform.

Questioned Cost
0
Close Date
Oct 30, 2009
Recommendation
4

USAID/Guatemala, in coordination with its implementing partners, establish procedures for systematically evaluating and following up with training participants as appropriate to assess the impact and effectiveness of training.

Questioned Cost
0
Close Date
Sep 23, 2010
Recommendation
5

USAID/Guatemala make a determination of eligibility for $36,238 in unsupported leverage contributions and $598,188 in ineligible contributions under the Youth Alliance Program and for any shortfalls in contributions obtain additional contributions under the current Youth Challenge Program.

Questioned Cost
634426
Close Date
Mar 22, 2010
Recommendation
6

USAID/Guatemala verify that Creative Associates has implemented a satisfactory system for valuing volunteer work under the program.

Questioned Cost
0
Close Date
May 07, 2010
Recommendation
7

USAID/Guatemala, in conjunction with its implementing partners, develop and implement a system to reasonably ensure that reported information is accurate.

Questioned Cost
0
Close Date
Nov 29, 2010
Recommendation
8

USAID/Guatemala develop a performance management plan for its follow-on democracy and governance program that meets USAID policy requirements.

Questioned Cost
0
Close Date
Sep 29, 2010
Oct 27, 2009
Audit Report
6-263-10-001-P
Recommendation
1

USAID/Egypt develop and document a training plan for assistance recipients to explain USAID rules, regulations, and expectations, prior to beginning activities.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
2

USAID/Egypt develop and document a training plan to provide its democracy and governance staff refresher training on how to effectively manage programs including contracting and financial management responsibilities.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
3

USAID/Egypt document a review of its programs to determine whether a mission-wide order on antiterrorism measures would help to mitigate the mission's risk of inadvertently providing financing to terrorist organizations or individuals associated with terrorism.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
4

USAID/Egypt document and provide training to the democracy and governance implementers on USAID's antiterrorism measures.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
5

USAID/Egypt develop a standardized checklist to document management reviews as a part of democracy and governance program assessments.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
6

USAID/Egypt make a management decision on the questioned cost sharing and recover estimated cost share contributions of $8,493 identified for amounts deemed payable.

Questioned Cost
8493
Close Date
Oct 27, 2009
Recommendation
7

USAID/Egypt document a review of the democracy and governance agreements' financial information to determine if appropriate cost share contributions have been made and document a plan to recover any outstanding contributions.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
8

USAID/Egypt develop a written plan to require its technical representatives to provide certifications about training participants' noncompliance with documentation requirements, which would be reported to the mission director immediately to limit potential governmental liabilities.

Questioned Cost
0
Close Date
Sep 23, 2010
Recommendation
9

USAID/Egypt explore and document possibilities to recover the unused equipment and put it to immediate and better use within 15 days.

Questioned Cost
0
Close Date
Oct 27, 2009
Recommendation
10

USAID/Egypt document a review of authorizing designation letters for its technical representatives to ensure that staff have appropriate authority to manage agreements and administratively approve financial payments.

Questioned Cost
0
Close Date
Oct 27, 2009
Oct 09, 2009
Audit Report
5-492-10-001-P
Recommendation
1

USAID/Philippines develop and implement procedures that require the agreement officer's technical representative to review the Sustainable Health Improvements through Empowerment and Local Development Project in the Autonomous Region of Muslim Mindanao's performance management plan on an annual or semiannual basis to ensure that it contributes to an effective system of measuring progress toward intended objectives.

Questioned Cost
0
Close Date
Oct 22, 2010
Recommendation
2

USAID/Philippines provide written guidance to its implementers as to what constitutes "training" for purposes of reporting project performance.

Questioned Cost
0
Close Date
Oct 09, 2009
Recommendation
3

USAID/Philippines develop and implement procedures that require its agreement officer's technical representative to periodically conduct an independent review of the performance data submitted by implementers.

Questioned Cost
0
Close Date
Oct 22, 2010
Oct 08, 2009
Audit Report
7-660-10-001-P
Recommendation
1

USAID/Democratic Republic of Congo update the Displaced Children and Orphans Fund's performance management plan in accordance with USAID guidance and develop specific procedures to assign responsibility for regularly updating the document.

Questioned Cost
0
Close Date
Sep 24, 2010

2009

Sep 30, 2009
Audit Report
M-000-09-006-P
Recommendation
1

Recommendation 1: We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, define development impact and reasonable financial return and develop specific measures and targets for use in evaluating the Georgia Regional Development Fund's performance against its primary objective.

Questioned Cost
0
Close Date
Sep 16, 2010
Recommendation
2

Justify the Fund Manager's existing compensation arrangement (see page 9)

Questioned Cost
0
Close Date
Sep 30, 2009
Recommendation
3

Require that the Fund Manager develop policy and procedures for conducting character due diligence for each investee and for documenting the results of the character due diligence (see page 11)

Questioned Cost
0
Close Date
Jun 13, 2011
Recommendation
4

We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, provide the Fund Manager with current Millennium Challenge Corporation guidance on vetting of individuals and organizations receiving United States taxpayer funding.

Questioned Cost
0
Close Date
Sep 30, 2010
Recommendation
5

We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, require that the Fund Manager identify and document the environmental laws, regulations, and requirements relevant to the investments.

Questioned Cost
0
Close Date
Jun 11, 2010
Recommendation
6

We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, require that the Fund Manager review its loan agreements with investees and specify actions in the agreements with regard to the asbestos.

Questioned Cost
0
Close Date
Jun 13, 2011
Recommendation
7

We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, require periodic environmental reviews by Millennium Challenge Georgia of the Georgia Regional Development Fund's investments and ensure that environmental audits are done when required.

Questioned Cost
0
Close Date
Jun 13, 2011
Recommendation
8

We recommend that the Millennium Challenge Corporation's vice president, Department of Compact Implementation, revise the Fund Management Agreement Investment Policy Guidelines to include guidelines preventing investments in investees with resources to fund their own projects.

Questioned Cost
0
Close Date
Jun 11, 2010
Sep 30, 2009
Audit Report
M-000-09-005-P
Recommendation
1

We recommend that the Millennium Challenge Corporation's Vice President for Compact Implementation require the Millennium Development Authority to revise and implement a procedure that would ensure that participating financial institutions' loan payments are paid into the Millennium Development Authority repayment account at the Bank of Ghana, as required by the Agricultural Credit Program Policy and Procedure Manual.

Questioned Cost
0
Close Date
Oct 21, 2011
Recommendation
2

We recommend that the Millennium Challenge Corporation's Vice President of Compact Implementation require the Millennium Development Authority establish and implement a process for the Bank of Ghana to monitor loan repayments which identify participating financial institutions that have missed payments.

Questioned Cost
0
Close Date
Oct 21, 2011
Recommendation
3

We recommend that the Millennium Challenge Corporation's Vice President for Compact Implementation require the Bank of Ghana and the Millennium Development Authority to establish and implement a borrowing limit for each of the accredited participating financial institutions by September 30, 2009.

Questioned Cost
0
Close Date
Sep 30, 2009
Recommendation
4

We recommend that the Millennium Challenge Corporation's Vice President for Compact Implementation require the Millennium Development Authority to develop and implement procedures in order for the Bank of Ghana to conduct annual reviews of the participating financial institutions before their accreditation expires.

Questioned Cost
0
Close Date
Oct 21, 2011
Recommendation
5

We recommend that the Millennium Challenge Corporation's Vice President for Compact Implementation require the Millennium Development Authority to validate, by September 30, 2009, that the Bank of Ghana is implementing the process by which participating financial institutions will sign a loan agreement before the Bank of Ghana disburses their loans.

Questioned Cost
0
Close Date
Oct 21, 2011
Sep 30, 2009
Audit Report
M-000-09-007-P
Recommendation
1

We recommend that the Millennium Challenge Corporation's vice president for Compact Implementation develop and document a Millennium Challenge Corporation/Millennium Challenge Georgia Fund action plan, which lays out construction milestones and related activities that need to take place, to ensure the Samtskhe-Javakheti Road Rehabilitation Project is completed within the time period of the compact.

Questioned Cost
0
Close Date
Jun 10, 2010
Recommendation
2

We recommend that the Millennium Challenge Corporation's vice president for Compact Implementation request that the Millennium Challenge Georgia Fund obtain from the contractor from the initial advance, the amount of $2,316,824.27, which would now be considered an overpayment on the section.

Questioned Cost
0
Close Date
Oct 04, 2011
Recommendation
3

We also recommend that the Millennium Challenge Corporation's vice president of Compact Implementation have an audit conducted to determine how the advance payment was used to cover the cost of mobilization.

Questioned Cost
0
Close Date
Jun 10, 2010
Sep 29, 2009
Audit Report
4-650-09-009-P
Recommendation
1

USAID/Sudan develop policies and procedures to help ensure future feasibility studies of USAID-funded projects are provided with a) adequate funding and scheduling, and b) unambiguous instructions regarding the nature and extent of technical analyses to be performed.

Questioned Cost
0
Close Date
Mar 18, 2010
Recommendation
2

USAID/Sudan retain a consulting engineer at least through the estimated completion date of the Juba-Nimule road.

Questioned Cost
0
Close Date
Mar 18, 2010
Recommendation
3

USAID/Sudan revise its branding strategy for the Juba-Nimule road project to focus more on direct communication with project beneficiaries.

Questioned Cost
0
Close Date
Mar 18, 2010
Recommendation
4

USAID/Sudan determine whether its recipients' subawards contain the required provision concerning the implementation of Executive Order 13224 and require that the recipients incorporate the required provision into any subawards from which it was omitted.

Questioned Cost
0
Close Date
Mar 18, 2010
Sep 02, 2009
Audit Report
1-526-09-010-P
Recommendation
1

USAID/Paraguay, in coordination with the implementing partner and the Government of Paraguay, establish an action plan with benchmarks and timeframes to assess the capabilities of staff in the forensics laboratory and provide necessary training, complete the implementation of strengthened internal controls in five ministries, and implement an online interface for public registry information.

Questioned Cost
0
Close Date
Sep 30, 2010
Recommendation
2

USAID/Paraguay include a clause in the agreement for the second threshold program that would allow it to recover any expenditures that are wasted as a result of failure of the Government of Paraguay to fulfill its obligations under the agreement.

Questioned Cost
0
Close Date
Sep 02, 2009
Recommendation
3

USAID/Paraguay focus border and customs control activities during the follow-on program on Ciudad del Este.

Questioned Cost
0
Close Date
May 11, 2010
Recommendation
4

USAID/Paraguay, in coordination with its implementing partners establish procedures to track statistics on outcomes related to complaints of judicial misconduct, customs law enforcement actions, and tax and customs evasions cases.

Questioned Cost
0
Close Date
Sep 28, 2010
Recommendation
5

USAID/Paraguay, in coordination with DETAVE, verify that all maintenance issues and/or manufacturing defects have been resolved to put the 10 idle boats costing $357,320 in operation.

Questioned Cost
0
Close Date
Sep 21, 2010
Recommendation
6

USAID/Paraguay ensure that DETAVE develops and implements an action plan for maintaining and using the boats.

Questioned Cost
0
Close Date
Dec 28, 2009
Recommendation
7

USAID/Paraguay formalize a procedure to conduct periodic end-use checks for commodities purchased under the program.

Questioned Cost
0
Close Date
May 11, 2010
Recommendation
8

USAID/Paraguay, in coordination with its partners, budget for and schedule an independent security assessment of the identification and passport system as soon as possible.

Questioned Cost
0
Close Date
Sep 28, 2010