Recommendation Dashboard

OIG makes recommendations in our reports to improve the efficiency and effectiveness of agency programs and help agencies identify questioned costs and funds that could be put to better use. The aim is to spur our audited agencies to take corrective actions, which allow us to close the recommendations.

This dashboard identifies current open recommendations along with the associated questioned costs.  Open recommendations may be resolved or unresolved:

  • A recommendation is resolved when OIG agrees with the agency's plan of action.
  • A recommendation is unresolved when the agency has yet to share a plan of action or OIG disagrees with the plan.

The dashboard below may not reflect accurate numbers due to temporarily unavailable resources. We apologize for any inconvenience. Please check back soon.

 

Total Open Recommendations (As of 6/27/24)

256

Open Financial Recommendations (As of 6/27/24)

$108,584,846


Please see an updated list of recommendations with their corresponding report below.

2021

Jun 23, 2021
NFA Transmittal
3-000-21-020-R
Recommendation
1

We recommend that USAID's Office of Acquisition and Assistance, Cost, Audit and Support Division determine the allowability of $224,596 of questioned direct costs ($2,243 ineligible and $222,353 unsupported) on the revised fund accountability statement, following Appendix 2a and Appendices 2b/1 through 2b/4, 3/2 through 3/3 and 4/1 through 4/3 of the audit report and recover any amount that is unallowable.

Questioned Cost
224596
Funds for Better Use
0
Close Date
Apr 26, 2023
Recommendation
2

We recommend that USAID's Office of Acquisition and Assistance, Cost, Audit and Support Division verify that Hanns R. Neumann Stiftung corrects the material weakness detailed on Appendices 3/2 through 3/3 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Mar 22, 2022
Recommendation
3

We recommend that USAID's Office of Acquisition and Assistance, Cost, Audit and Support Division verify that Hanns R. Neumann Stiftung corrects the two instances of material noncompliance detailed on Appendices 4/1 through 4/3 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Mar 22, 2022
Jun 23, 2021
NFA Transmittal
4-615-21-009-N
Recommendation
1

We recommend that USAID/Kenya and East Africa verify that Population Services Kenya corrects the two instances of material noncompliance detailed on pages 35 and 37 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Feb 28, 2022
Jun 21, 2021
NFA Transmittal
4-621-21-069-R
Recommendation
1

We recommend that USAID/Tanzania determine the allowability of $163,290
in unsupported questioned costs on page 33 of the audit report and recover any amount that is unallowable.

Questioned Cost
163290
Funds for Better Use
0
Close Date
Sep 26, 2022
Recommendation
2

We recommend that USAID/Tanzania verify that National Council of People
Living with HIV and AIDS corrects the five instances of material noncompliance detailed on pages 30 to 34 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Sep 26, 2022
Jun 11, 2021
NFA Transmittal
5-391-21-030-R
Recommendation
1

Determine the allowability of $28,197 in questioned cost-sharing contributions (ineligible) as detailed in Findings 4.4.2, 4.2.3, and 4.2.4 on pages 34-37 of the report, and recover any amount that is unallowable.

Questioned Cost
28197
Funds for Better Use
0
Close Date
Mar 17, 2022
Recommendation
2

Determine the allowability of $168,316 (ineligible) in questioned amounts related to penalty not imposed to contractors on delayed completion of work as detailed in Finding 4.1.2 on pages 31-32 of the report, and recover any amount that is unallowable.

Questioned Cost
168316
Funds for Better Use
0
Close Date
Mar 17, 2022
Recommendation
3

Determine the allowability of $1,250,424 (ineligible) in questioned costs as detailed in Table 1 on page 2 of this memorandum, and recover any amount that is unallowable.

Questioned Cost
1250424
Funds for Better Use
0
Close Date
Mar 17, 2022
Recommendation
4

Determine the allowability of $2,640,051 (ineligible) in questioned amounts related to cumulative payments as of June 2020 to various contractors on construction works that were not in accordance with rules and procedures as detailed in Finding 4.4.1 on pages 40-41 of the report, and recover any amount that is unallowable.

Questioned Cost
2640051
Funds for Better Use
0
Close Date
Mar 17, 2022
Jun 11, 2021
NFA Transmittal
5-492-21-029-R
Recommendation
1

Determine the allowability of $34,253 ($17,905 ineligible and $16,348 unsupported) in questioned costs as detailed in Findings 2, 4, and 5 on pages 25 to 29 of the audit report and recover any amount that is unallowable.

Questioned Cost
34253
Funds for Better Use
0
Close Date
Jun 29, 2022
Jun 10, 2021
NFA Transmittal
3-000-21-041-I
Recommendation
1

We recommend that the USAID's Office of Acquisition and Assistance Cost, Audit and Support Division determine the allowability of $389,803 in total direct questioned costs ($389,803 unsupported) on pages 5, through 7, and 53 through 61 of the report and recover any amount that is unallowable.

Questioned Cost
389803
Funds for Better Use
0
Close Date
Jun 09, 2022
Recommendation
2

We recommend that the USAID's Office of Acquisition and Assistance Cost, Audit and Support Division verify that Palladium International, LLC corrects the material weakness in internal control detailed on pages 2 and 16 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Apr 28, 2022
Jun 09, 2021
NFA Transmittal
8-306-21-034-N
Recommendation
1

Determine the allowability of $6,851,149 in questioned unsupported costs detailed on pages 7-8 of the audit report and recover any amount that is unallowable.

Questioned Cost
6851149
Funds for Better Use
0
Close Date
May 04, 2022
Jun 03, 2021
NFA Transmittal
3-000-21-039-I
Recommendation
1

We recommend that USAID's Office of Acquisition and Assistance Cost, Audit and Support Division verify that Visionary Consulting Partners, LLC corrects the material weakness in internal control detailed on pages 13 and 14 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Jan 21, 2022
Jun 02, 2021
NFA Transmittal
8-306-21-033-N
Recommendation
1

Determine the allowability of $34,447 in ineligible questioned costs on page 23 of the audit report and recover any amount that is unallowable.

Questioned Cost
34447
Funds for Better Use
0
Close Date
Sep 27, 2022
Recommendation
2

Verify that FHI 360 corrects the two material instances of noncompliance detailed on pages 23 to 26 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Aug 17, 2022
May 21, 2021
NFA Transmittal
4-674-21-059-R
Recommendation
1

We recommend that USAID/Southern Africa verify that Humana People to People in South Africa corrects the one instance of material noncompliance detailed on page 26 of the audit report.

Questioned Cost
0
Funds for Better Use
0
Close Date
Sep 21, 2021